【摘要】 土谷塘电站地处湘江中游的衡阳市衡南县,计划于2011年初建成投产。研究表明,该电站送电真武220 kV变供电区,并通过1回110 kV线路接入系统是适宜的。
【Abstract】 Tugutang hydropower station,located at Hengnan county of Hengyang,is up to put into operation in 2011.The study indicated that it is proper to connect TuGuTang hydropower station into Hunan power grid with one 110kV transmission line delivering power to Zhenwu 200 kV substation.
【关键词】 接入系统;
出线间隔;
潮流分布;
综合年费用;
远景适应性;
【Key words】 connecting system; outgoing line interval; load distribution; overall annual cost; long-range adaptability;
【Key words】 connecting system; outgoing line interval; load distribution; overall annual cost; long-range adaptability;