顶推法施工珠江西桥时后移制梁台座的分析

Analysis of Influences from Shifting Backward Girder Precasting Bed During Incremental Launching Construction of Zhujiang River West Bridge

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 林俊锋王卫锋马文田

【Author】 LIN Jun-feng~1, WANG Wei-feng~1, MA Wen-tian~2(1. South China University of Technology, Guangzhou 510640, China; 2. Admin-istration of Highways, Guangzhou City, Guangzhou 510080, China)

【机构】 华南理工大学广州市公路管理局 广东广州510640广东广州510640广东广州510080

【摘要】 在广州市内环路广佛出口放射线珠江大桥西桥的实际施工方案里,对制梁台座的位置作了后移,通过计算和分析,得出制梁台座后移这一变更对整个顶推施工过程的影响,并对制梁台座后移的施工方案的优点和不利之处作了归纳。

【Abstract】 In the actual erection scheme for Zhujiang River West Bridge on the radial roads at the exit Guangzhou to Foshan on the Inner Ring Road of Guangzhou City, the position of the girder precasting bed used for incremental launching construction of the Bridge is varied by shifting the bed backward. In this paper, the influences from variation of shifting the bed on the whole process of the incremental launching construction are analyzed through computation, and comments on both the advantages and disadvantages of the varied erection scheme are made as well.