新城金矿-175m中段1763采场采矿方法改进
The improvement of mining method in stope 176 of level -175m in Xincheng Gold Mine
【摘要】 介绍新城金矿 -1 75m中段 1 763采场采矿方法改进过程。应用盘区机械化上向水平分层尾砂胶结充填采矿法 ,回采该采场的三分层、四分层 ,将采矿损失率降至4 4 %,取得了较好的经济效益。
【Abstract】 The process of the improvement of mining method in stope 176 of level -175m in Xincheng Gold Mine was introduced.Using panel mechanization,the rd and 4th slices of stope 176 were mined by method of upward horizontal slicing and consolidated fill with tailing.By this mining method ,the ore loss rate of mining reduced to 4.4%,gaining better economic benefit.
【关键词】 上向水平;
尾砂充填;
盘区机械化;
采矿损失率;
【Key words】 upward horizon; filling with tailing; panel mechanization; ore loss rate of mining;