察汗乌苏电站水轮机尾水管的安装
Installation of draft tube of hydraulic turbine for Chahanwusu power station
【摘要】 在水轮机的安装过程中,设备安装和混凝土浇筑工作交替进行,互相影响。察汗乌苏电站水轮机的尾水管尾水肘管和尾水锥管,其施工工程也是分步进行的。调整尾水管断面的水平偏差、位置偏差、高程偏差的方法来实现安装,这也是尾水管安装的关键技术。
【Abstract】 During the installation of hydraulic turbine,erecting and concreting alternately,they affected each other.The draft tube of hydraulic turbine for Chanwusu powerstaion is made up of draft tube elbow and draft tube cone,its installation will be finished by step.Ajusting the tolerence of the level,the tolerance of the evlevation,the tolerence of the position is the main methord,it is the key technology for installation.
- 【文献出处】 应用能源技术 ,Applied Energy Technology , 编辑部邮箱 ,2007年04期
- 【分类号】TK730.3
- 【下载频次】54