基于TOC的模具生产多项目管理研究
Research on multiple project management of die&mould production based-on TOC
【摘要】 在分析多项目管理发展的基础上,根据模具生产模式特点,构建汽车零/部件模具制造多项目实例,以工期为评估标准,运用约束理论(Theory of Constraint,TOC)的关键链管理技术(CCPM)进行多项目计划创建与控制,同时利用Pro-ject2003项目管理软件(关键路径法)实现此过程,对比两种结果显示,完工保证率为90%情况下,运用关键链管理技术(CCPM)项目平均完工时间为83h,运用关键路径法(CPM)平均完工时间为109h,效率提高约20%。
【Abstract】 Analyze the development of multiple project management first,on the basis of the characteristic of die&mould production mode,build a sample of automobile components mould manufacturing multi-project,view project time as evaluating standard,applying CCPM(Critical Chain Project Management)based on TOC(Theory of Constraint) to construct and control multi-project,meanwhile,using Project2003 project management software(Critical Path Method,CPM)to realize it ,the result shows that CCPM can reduce the average completion time by almost 20%,whilst the completion time with 90% probability using the CCPM is 83 hours,compared with 109 hours by traditional CPM method.
【Key words】 Multi-project management; Critical chain project management; Project2003; Die&mould production management;
- 【文献出处】 现代制造工程 ,Modern Manufacturing Engineering , 编辑部邮箱 ,2007年03期
- 【分类号】TG76
- 【被引频次】34
- 【下载频次】357