节点文献
浅谈连续梁施工中如何有效控制预拱度的问题
Measures to realize effective control of camber setting in construction of continuous beam
【摘要】 针对连续梁在悬臂浇筑施工中,梁段立模标高的合理确定关系到梁的纵断面线形是否顺滑、是否符合设计的一个重要问题,通过对各种影响因素的分析,提出了针对性的方案,解决了考虑因素与实际不相符,控制不力,发生较大偏离的问题。
【Abstract】 The rational determination of elevation of erected formwork in beam part is an important question related to the smoothness of the linear of longitudinal section to meet design requirements.Based upon analysis of the various influencing factors corresponding scheme is proposed to resolve questions encountered in practice,which cause large deviation with practice.
- 【文献出处】 山西建筑 ,Shanxi Architecture , 编辑部邮箱 ,2007年25期
- 【分类号】U445.466
- 【被引频次】2
- 【下载频次】133