海底隧道工程盾构始发井水下封底混凝土施工

Construction Technology of Underwater Concrete Casting for Bottom-sealing of Launch Shaft of a Sub-sea Shield-driven Tunnel

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 谢仁根

【Author】 XIE Ren-gen(The 1st TBM Construction Branch of the 2nd Engineering Co.,Ltd.of China Railway Tunnel Group,Yanjiao 101601,Beijing,China)

【机构】 中铁隧道集团二处有限公司掘进一工程公司 北京燕郊101601

【摘要】 深圳前湾过海隧道工程盾构始发竖井,直径18m,深28.54m,采用沉井法施工,水下混凝土封底,封底厚度4.5 m。属大体积混凝土施工,如何保质、保量、按期完成封底工作,是一个值得研究的问题。结合工程实际及相关计算理论,介绍了高水压海滩地层中盾构始发井井底水下大体积、大面积、封底混凝土施工技术。

【Abstract】 The diameter and depth of the launch shaft of Qianwan sub-sea shield-driven tunnel in Shenzhen are 18 m and 28.54 m respectively.The lauch shaft is sunk by means of open caisson method.During the sinking of the launch shaft,underwater bottom-sealing is conducted.With a thickness of 4.5 m,the concrete casting of the bottom-sealing construction belongs to huge-volume concrete casting construction.It is worthy to make study on the concrete casting construction so as to fulfill the bottom-sealing with high quality and as per the schedule.On basis of the actual conditions of the project and the relevant theoreatical calculations,the article presents the construction technology of the huge-volume and large-cross-section underwater concrete casting for the bottom-sealing of the launch shaft situated in coastal ground.