【作者】 王晓放李存德宋玉香

【Author】 Wang Xiaofang 1) Li Cunde 2) Song Yuxiang 3) (School of Adult Education 1) ,School of Civil Engineering 3) ,Shijiazhuang Railway Institute,Shijiazhuang 050043 Xinji Municipal Engineering Cpmpany 2) , Xinji 052360)

【机构】 石家庄铁道学院成人教育分院辛集市市政工程公司石家庄铁道学院土木工程分院 石家庄050043辛集052360石家庄050043

【摘要】 博山 2号双跨连拱隧道采用三导洞钻爆法施工 ,中导洞超前 ,两侧导洞滞后 ,待中隔墙完成后进行侧导洞扩挖。为保证施工安全 ,采用有限元程序对扩挖过程进行分析 ,得出中隔墙的最大震动速度

【Abstract】 Boshan No.2 tunnel is a double arch tunnel,it was excavated by drill and blast with three pilots,the middle pilot was first excavated,followed by the lateral pilots which would be enlarged after the middle wall had been built.In order to ensure the safety of middle wall,the blasting vibration effect are analyzed by means of FEM in this paper.

  • 【文献出处】 石家庄铁道学院学报 ,Journal of Shijiazhuang Railway Institute , 编辑部邮箱 ,2002年S1期
  • 【分类号】U451
  • 【被引频次】21