回路分析法计算与调整施工网络计划
Calculation and Readjustment of the Network Plan with Circuit Analysis
【摘要】 回路分析法按下面计算顺序计算施工网络计划 ,即先确定网络的关键路线 ,计算网络图中各工作的时差 ,调整工作的活动时间 ,最终计算各工作的开始和完成时间 ,获得满足工期要求的网络计划。
【Abstract】 The methods of calculation & readjustment of construction network plan with circuit analysis are presented in this paper. The culculation steps are looking for the critical paths of the network plan, then the float times, and readjustments of activity time, at last calculation of the start time and the finish time for every works in the plan. In constrast to the conventional colculation, the method can avoid unnecessary repetition calculations.
【关键词】 网络计划;
计算;
调整;
回路分析;
【Key words】 construction network plan; calculation; readjustment; circuit analysis;