节点文献
HTR-10全厂断电试验
Plant Power Cut-off Test of the HTR-10
【摘要】 10MW高温气冷实验堆在电气系统的设计中,针对全厂断电设计基准事故采取了相应的处理措施。在10MW高温气冷实验堆热态性能调试期间进行了全厂断电试验,用以验证10MW高温气冷实验堆应急供电系统的功能。结果表明,在发生全厂断电的设计基准事故时,由蓄电池组支持的不间断交流电源装置可以可靠地保证各专设安全设施完成其安全功能,并能为反应堆事故监测提供20小时的电力供应。
【Abstract】 The special process was utilized for the design basis accident of plant power cut off in design of the HTR 10 power system.The plant power cut off test was done in the course of the HTR 10 hot testing in order to verify the function of the HTR 10 emergency power supply system.The result of the experiment has shown that the UPS,supplied by the battery,can ensure all engineered safety features to finish their safety function reliably and can supply 20 hours power energy for the demand of the HTR 10 accident supervision and measure.
【Key words】 MW High temperature gas cooled reactor(HTR 10); Plant power cut off test; Design basis accidents;
- 【文献出处】 核动力工程 ,Nuclear Power Engineering , 编辑部邮箱 ,2001年06期
- 【分类号】TL364
- 【被引频次】1
- 【下载频次】69