某曲线连续梁桥顶升高度偏差原因分析及应对措施

Cause Analysis and Countermeasures of Jacking Height Deviation of a Continuous Beam Bridge

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 王海张能伟吴二军苟金成

【Author】 Wang Hai;Zhang Nengwei;Wu Erjun;Gou Jincheng;Shanghai Tonggang Architectural Engineering Co.,Ltd.;College of Civil and Transportation Engineering,Hohai university;

【机构】 上海同罡建筑工程有限公司河海大学土木与交通学院

【摘要】 曲线桥梁整体顶升工程中,顶升位移的同步控制是关键性技术的难点,实际工程经常出现偏差较大现象,甚至可能发生安全事故。对曲线连续桥梁顶升中外侧位移偏高的2种可能原因进行分析。在有限元内力计算和现场监测基础上给出某三跨曲线连续箱形梁顶升偏差产生的原因,提出通过对其顶升动力与位移监控系统编组调整的曲线桥平衡顶升措施。

【Abstract】 Synchronous control of jacking displacement is a key technical difficulty in the integral jacking engineering of curved bridge.Significant deviation usually happened in actual project,and a safety accident may even been brought out.Two possible reasons why the jacking displacement of outer edge of the bridge is higher were discussed.Taking a three span curved continuous box girder as the example,based on the finite element calculation of internal force and the field monitoring,the reason of jacking deviation was given.In order to reduce the jacking deviation,the balance jacking measures by adjusting groups of the lifting jacks and the displacement monitoring points were put forward.

  • 【会议录名称】 第十一届建筑物改造与病害处理学术研讨会、第六届工程质量学术会议论文集
  • 【会议名称】第十一届建筑物改造与病害处理学术研讨会、第六届工程质量学术会议
  • 【会议时间】2016-12-02
  • 【会议地点】中国海南海口
  • 【分类号】U445.4
  • 【主办单位】中国老教授协会土木建筑专业委员会、中国土木工程学会工程质量分会、北京交通大学土木建筑工程学院