曹妃甸11油田FPSO上部模块设计中设施预留能力的考虑

The method of Pre-debottlenecking used in CFD 11 FPSO topsides facilities engineering

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 方福胜

【Author】 Fang Fusheng (CNOOC Research Center, Beijing, 100027, China)

【机构】 中海石油研究中心

【摘要】 工艺系统中的管线和客器等设备一旦安装就位,将来很难再改变,它们是制约工程设施将来扩大处理能力的“瓶颈”,在设上要一步到位;而发电机组、锅炉和注水泵组等价格昂贵的设备,只需在模块上预留安装位置,待需要时安装印可,这就是工程设计中“预先消除瓶颈”的概念。曹妃甸11油田采用“预先消除瓶颈”的方法,解决了工程设施的预留能力问题。

【Abstract】 Once the piping and vessels in prcess system are installed on Topside it is hard to modify in the future. Therefore they are bottleneck which restrict Topside facilities to increase throughput in the future, and should be designed based on maximum throughput. However, expensive equipment like power generators, boilers and water injection pumps can be installed in the future as long as the installation space has been left. This is the method of pre-de-bottlenecking in facilities design. By using the method of Pre-debottlenecking in CFD 11 FPSO topsides facilities engineering, the maximun capacity of topside facilities has been speicified.

  • 【会议录名称】 2006年度海洋工程学术会议论文集
  • 【会议名称】2006年度海洋工程学术会议
  • 【会议时间】2006-11
  • 【会议地点】中国广西南宁
  • 【分类号】TE54
  • 【主办单位】中国造船工程学会近海工程学术委员会
节点文献中: 

本文链接的文献网络图示:

本文的引文网络