安钢6号高炉长期休风及复风操作实践
Operation practice of long term blowing-down and reblowing on Anyang Steel’s No.6 BF
【Author】 Niu Weijun Zhang Xiaoliang Tian Liming Zhang Haizhou (Anyang Iron & Steel Group Co.,Ltd)
【机构】 安阳钢铁集团有限责任公司;
【摘要】 安钢6号高炉长期休风33.5小时计划检修,送风后近9个小时恢复正常生产,整个过程避免了风口烧坏事故。本文对这次休复风操作进行了总结,并分析了全开风口送风等恢复炉况的方法。
【Abstract】 Long term blowing-down for 33.5 hours was carried out because of plan overhaul at Anyang Steel’s No.6 BF,after reblowing it took nearly 9 hours to achieve the BF normal condition,the operation had avoided the burn-out of tuyere accident in the entire process.This essay summarizes the blowing-down and reblowing operation, analyzes the methods of resuming BF condition,such as reblowing with opening all tuyeres and so on.