基于BIM的地下金属矿区垮塌注浆加固风险数值模拟

Numerical Simulation of Collapse and Grouting Reinforcement Risk in Underground Metal Mines Based on BIM

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 曹萍王帮建李强侯博雯

【Author】 CAO Ping;WANG Bang-jian;LI Qiang;HOU Bo-wen;School of Architecture and Civil Engineering, Xi′an University of Science and Technology;

【通讯作者】 王帮建;

【机构】 西安科技大学建筑与土木工程学院

【摘要】 为获取最优注浆参数,利用BIM技术实现了地下金属矿区垮塌注浆加固风险数值模拟。选取某地铅锌矿主矿体中段1号采场3分段作为注浆加固数值模拟对象,数值模拟结果表明:浆液扩散半径随注浆压力以及注浆时间增加而有所提升;利用数值模拟结果确定最优化学注浆参数,采用所确定的化学注浆参数注浆加固后垮塌区域岩体质量明显提升。

【Abstract】 In order to obtain the optimal grouting parameters, BIM-based technology was used to realize the numerical simulation of collapse and grouting reinforcement risk in underground metal mines. The 3rd section of №1 stope in the middle section of the main ore body of a lead-zinc mine was selected for the numerical simulation of grouting reinforcement. The numerical simulation results showed that the slurry diffusion radius increased with the increase of grouting pressure and grouting time, and the optimal chemical grouting parameters were determined based on the numerical simulation results. As a result, the rock mass quality in the collapsed area is significantly improved after grouting with the determined chemical grouting parameters.

【基金】 陕西省自然科学基础研究计划项目(2017JM5045)
  • 【文献出处】 矿冶工程 ,Mining and Metallurgical Engineering , 编辑部邮箱 ,2020年04期