利用旁通洞方式解决过机泥沙问题的探索

Exploration on Solving Problem of Sediment Passing the Turbine by Bypass Tunnel

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 师广山任宏斌刘永智刘娜

【Author】 SHI Guangshan;REN Hongbin;LIU Yongzhi;LIU Na;PowerChina Northwest Engineering Corporation Limited;

【机构】 中国电建集团西北勘测设计研究院有限公司

【摘要】 结合河道流量大时含沙量高的特性和工程特点,依照分流分沙原理,探索利用导流洞在库区设置旁通洞,利用旁通洞进水口与电站进水口之间的水库形成沉沙池,在大流量时分流入库流量和泥沙,降低库内水流流速,加速泥沙沉降,解决过机泥沙问题。通过分析论证,表明设置旁通洞能够有效地解决工程泥沙问题,在技术、经济方面也具有优势。

【Abstract】 With consideration of the project features and engineering characteristics of high sediment content during large river flow, and in accordance with the principle of diversion and sedimentation, the article explores the use of diversion tunnel to set up bypass tunnel in the reservoir area, and form a sand basin by the reservoir between the bypass tunnel inlet and the power station intake. During large flow period, the discharge and sediment shall be diverted, reducing the flow velocity in the reservoir, accelerating sediment settlement, and solving the problem of sediment passing the turbine. Through analysis and demonstration, it is shown that the setting of the bypass tunnel can effectively solve the engineering sediment problem, and it is also superior in terms of technology and economy.

  • 【文献出处】 西北水电 ,Northwest Hydropower , 编辑部邮箱 ,2019年06期