针对昌江至铁矿厂110kV Ⅱ标段输电线路的杆塔定位与校验

Pole and tower spotting and calibration of electric transmission line of 110kV Ⅱ section in Changjiangzhi Iron Ore Plant

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 张博张艳雪李智

【Author】 ZHANG Bo;ZHANG Yan-xue;LI Zhi;Academy of electric and new energy,China Three Gorges University;

【机构】 三峡大学电气与新能源学院

【摘要】 本文主要研究的是昌江至铁矿厂110kV Ⅱ标段输电线路工程设计的具体流程,查询相关资料得到与设计有关的杆塔与导地线的数据,并运用相关公式对数据进行加工处理,在上述所得数据的基础上,运用CAD制图手段完成了杆塔的定位。在杆塔校验方面,通过CAD读图获取杆塔数据并完成其相关的定位校验。

【Abstract】 This paper mainly studies the detailed process of 110 kV Ⅱ section electric transmission line engineering of Changjiangzhi Iron Ore Plant,and the information about pole and tower and ground wire related to the design is inquired and obtained. Meanwhile,related formulas are used for data processing,and on the basis of the above-mentioned data,CAD drawing is adopted to complete pole and tower spotting. In terms of pole and tower calibration,the data of the pole and tower is acquired through CAD map reading to complete its related positioning and calibration.

  • 【文献出处】 电气传动自动化 ,Electric Drive Automation , 编辑部邮箱 ,2019年01期
  • 【分类号】TM75