节点文献

改建铁路邻近营业线特大桥承台施工及线路加固技术

Construction for Pile Caps and Line Reinforcement of Grand Bridge of Reconstructed Railway in the Vicinity Operating Railway

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 贾江坤魏海斌米怀军韩雷雷

【Author】 JIA Jiangkun;WEI Haibin;MI Huaijun;HAN Leilei;China Railway 16th Bureau Group Luqiao Engineering Co.Ltd.;College of Transportation, Jilin University;

【通讯作者】 韩雷雷;

【机构】 中铁十六局集团路桥工程有限公司吉林大学交通学院

【摘要】 本工程为改建铁路广梅汕线龙湖南至汕头段增建二线及厦深联络线工程第一标段,正线长度22.9km,正线特大桥12 680.46延长米/3座。本标段全线与既有广梅汕线平行,全线多处为邻近营业线施工,且标段范围内地质多为深厚软土层,故承台施工方法考虑采用钢板桩加型钢支撑支护开挖。此外,在桥墩承台施工前,对既有铁路进行了吊轨梁加固及钢花管注浆处理。本标段共计393个承台均已施工完成,结果均满足要求。

【Abstract】 This project is the second additional line of the reconstructed railway of Guangmeishan Line from Longhunan to Shantou and the first section of the linking-up road from Xiamen to Shenzhen. The length of main track is 22.9 km and there are 3 grand bridges per 12680.46 linear meter. The whole line of this section is parallel to the existing line and the construction will be carry out in the vicinity of the operating railway. Besides, most of the soil layer is deep-seated mollisol. Therefore, the construction method of pile cap adopts steel sheet pile and shaped steel support during the excavation and support processes. In addition, before the construction of pile cap, the existing railway is reinforced with rail beam and steel tube grouting. There are 393 pile caps in this section and all the construction has been completed. And the results meet the requirements.

  • 【文献出处】 施工技术 ,Construction Technology , 编辑部邮箱 ,2018年S4期
  • 【分类号】U445
  • 【被引频次】1
  • 【下载频次】41