淋溪河水电站溢洪道泄洪消能形式研究

Study on Flood-discharge and Energy Dissipation of Spillway in Linxihe Hydropower Station

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 刘立迩蔡宜洲

【Author】 LIU Li-er;CAI Yi-zhou;College of Hydraulic and Environmental Engineering,China Three Gorges University;

【机构】 三峡大学水利与环境学院

【摘要】 鉴于淋溪河水电站溢洪道原设计方案的种种缺陷,基于弗劳德准则,采用1∶60的模型比尺,通过设置表孔和深孔出口体型,研究了不同体型参数下泄流能力和水流对水垫塘底板的冲击压力。试验结果表明,优化后的底板冲击压力由14.50kPa降至11.44kPa,脉压均方根由95.67kPa降至45.55kPa,同时水垫塘长度由269.5m减小至169.5m,仍满足泄洪消能要求。研究成果可为同类工程提供参考。

【Abstract】 In view of the defects of the original design scheme of spillway in Linxihe hydropower station,based on the Froude principle and 1∶60 model scale,the impact pressure of the discharge capacity and water flow on the bottom plate of the water cushion was studied by setting the shape of crest and bottom outlets.The test results show that the optimized floor impact pressure dropped from 14.50 kPa to 11.44 kPa,the root mean square root of pulsating pressure was reduced from 95.67 kPa to 45.55 kPa as well as t he length of the water cushion pond decreased from 269.5 mto 169.5 m,which still meets the requirement of flood discharge.The research results can provide reference for similar projects.

【关键词】 消能水工模型表孔深孔
【Key words】 energy dissipationhydraulic modelcrest outletbottom outlet
  • 【文献出处】 水电能源科学 ,Water Resources and Power , 编辑部邮箱 ,2017年11期
  • 【分类号】TV651.1
  • 【被引频次】1
  • 【下载频次】69