节点文献
昆明市第九、第十地下污水处理厂设计实例分析
Design Principle of the Ninth and the Tenth Underground Wastewater Treatment Plants in Kunming City
【摘要】 昆明市第九、第十地下污水处理厂设计规模分别为10×104、15×104m3/d,主体工艺采用MBR技术。全部处理构筑物设于地下空间,地面用作城市绿化景观。介绍了这两座污水厂的工艺流程、主要构筑物和系统的工程设计,可供城市地下污水厂设计参考。
【Abstract】 The design capacity of the ninth and the tenth underground wastewater treatment plants( WWTPs) in Kunming City is 10 × 104 and 15 × 104m3/d,respectively,with main treatment process of membrane biological reactor( MBR) for both the plants. The two plants are constructed in underground while the ground/surface area was planned as urban landscape. This paper describes the major design principle,treatment process and main structures,which can provide reference for designing urban underground WWTP.
【关键词】 地下污水处理厂;
MBR;
地下空间;
【Key words】 underground wastewater treatment plant; MBR; underground space;
【Key words】 underground wastewater treatment plant; MBR; underground space;
- 【文献出处】 中国给水排水 ,China Water & Wastewater , 编辑部邮箱 ,2017年10期
- 【分类号】X703
- 【被引频次】11