人工挖孔抗滑桩护壁与桩身结构相互作用模型试验
Model Test of Interaction Between the Segmental Protection-wall and the Integral Pile Structure of Artificial Drilled Anti-slide Pile
【摘要】 为研究护壁结构对抗滑桩水平承载力的贡献,以某人工挖孔抗滑桩工程为背景,依据相似理论设计了1∶10的分段式护壁结构、整体式桩身结构模型,并通过2个MTS作动器分别同时施加水平位移荷载于条件完全相同的有护壁桩和无护壁桩桩顶,开展室内物理模型试验研究。结果表明:相同桩顶水平位移条件下,有护壁桩桩端土压力要大于无护壁桩桩端土压力,顶部桩前被动土压力要小于无护壁桩,加固柔性桩上部被动区土能更有效提高其水平承载能力。相同桩顶水平位移下,有护壁桩桩身受拉钢筋最大应变始终大于无护壁桩;随着桩顶水平位移的增加,桩身受拉钢筋最大应变截面逐渐下移,但有护壁桩下移滞后于无护壁桩;随着水平荷载的增加,有护壁桩桩身受拉钢筋最大应变增大比例先增加后减小,当桩顶水平位移为30 mm时达到最大,增大比例为165.03%,当桩顶水平位移为90mm时达到最小,增大比例为20.23%。若以桩顶水平位移为桩的水平承载力控制标准,试验护壁提高桩身水平承载力达20%以上,工程实践中可参考所提公式和折减系数来计算护壁对桩身水平承载力的贡献。
【Abstract】 In order to study the contribution of segmental protection-wall to the horizontal bearing capacity of anti-slide piles,based on an artificial drilled anti-slide pile engineering,the model structure of segmental protection-wall and integral pile was designed by using similarity theory. With two same actuators of MTS respectively loading horizontally on the top of pile with protection-wall and of pile with no protection-wall,a model test with the scale of 1∶ 10 was carried out to study the interaction of segmental protection-wall and integral pile structure of anti-slide pile under horizontal load. By simultaneously loading horizontally of MTS actuators,the following results were achieved. Firstly,with the same horizontal displacement of pile top,the soil pressure at the bottom of pile with segmental protection-wall is larger than that of pile with no protection-wall,but the passive soil resistance on the top of pile is reverse,and reinforcing of upper passive soil of flexible pile could improve the horizontal bearing capacity. Secondly,with the same horizontal displacement of pile top,the maximum strain of tensile steel bar of pile structure with segmental protection-wall is always larger than that of pile with no protection-wall. With the increase of horizontal displacement of pile top,the section position of maximum strain of tensile steel bar of pile is moving down,but the moving velocity of section position of pile with protection-wall loges behind that of pile with no protectionwall. Furthermore,with the increase of horizontal load,the proportion of maximum strain of tensile steel bar with protection-wall than that of with no protection-wall increass first and then decreases,and the maximum proportion is 165. 03% with the horizontal displacement of30 mm and the minimum proportion is 20. 23% with the horizontal displacement of 90 mm. Thirdly,with the horizontal displacement of pile top as the control standard of horizontal bearing capacity of pile,the horizontal bearing capacity of test pile in this paper increases more than 20%,and in the pile engineering practice,the contribution of horizontal bearing capacity improvement of segmental protection-wall can be computed by the formulas and reduction factor in the present work.
【Key words】 segmental protection-wall; artificial drilled anti-slide pile; interaction; horizontal displacement; model test;
- 【文献出处】 四川大学学报(工程科学版) ,Journal of Sichuan University(Engineering Science Edition) , 编辑部邮箱 ,2015年03期
- 【分类号】TU473.1
- 【被引频次】8