【摘要】 某海外项目由于深化设计空调负荷计算结果与招标设计空调负荷值存在很大差异,监理方不予审批,造成空调设备无法选型订货、空调风管不敢大规模施工,严重影响工期进度的极大困难状况,通过分析研究两阶段空调负荷计算书和复核计算,找到解决空调负荷计算矛盾的方法。

【Abstract】 There are significant differences between the deepening design of air conditioning load calculation results and the bidding design load value in an overseas project,the project was disapproved by the engineer,caused by air-conditioning equipment can not type selection and ordering,air-conditioning duct can not be large-scale construction,serious impact on the duration of the great difficulty of the situation,to find the calculation method to solve the contradiction of air conditioning load through the analysis of two stage air conditioning load calculation and checking calculation.

  • 【文献出处】 广东土木与建筑 ,Guangdong Architecture Civil Engineering , 编辑部邮箱 ,2015年11期
  • 【分类号】TU831.2
  • 【被引频次】1
  • 【下载频次】43
节点文献中: 

本文链接的文献网络图示:

本文的引文网络