节点文献

基于改进LMD的电能质量扰动检测新方法

A New Power Quality Disturbance Detection Method Based on the Improved LMD

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 宋海军黄传金刘宏超陈铁军李景丽罗勇

【Author】 SONG Haijun;HUANG Chuanjin;LIU Hongchao;CHEN Tiejun;LI Jingli;LUO Yong;School of Engineering and Technology, Zhongzhou University;Hunan Electric Power Design Institute;Zhengzhou University;

【机构】 中州大学工程技术学院湖南省电力勘测设计院郑州大学电气工程学院

【摘要】 介绍了一种新的非线性、非平稳信号分析方法——局部均值分解(local mean decomposition,LMD),分析了LMD用于扰动信号检测时的优缺点及原因。在此基础上,提出一种改进的局部均值分解(improved local mean decomposition,ILMD)电能质量扰动检测及时频分析新方法,该方法由LMD和希尔伯特变换(Hilbert Transform,HT)2部分组成。先用LMD提取信号的乘积函数(product function,PF),由PF分量的调幅函数可得信号瞬时幅值;再对PF分量进行HT求取瞬时频率。ILMD方法可有效定位发生扰动的起止时刻,克服LMD在定位能力上的不足。与采用希尔伯特黄变换(Hilbert Huang transform,HHT)方法相比,ILMD具有瞬时幅值函数端部失真小、瞬时幅频曲线波动小和幅值与频率检测精度高等优点。仿真信号和500 kV变电站电容器组投切时的电压信号分析结果证明所提方法的可行性和有效性。

【Abstract】 A new signal analysis method of non-linear, non-stationary—local mean decomposition(LMD) was introduced. The advantages and disadvantages of the application of LMD in the disturbance signal detection were analyzed. On this basis, the paper presented an improved local mean decomposition(ILMD) power quality disturbance detection and time-frequency analysis method. The method was composed of two parts: LMD and Hilbert transform. Firstly, to extract the product function(PF) of the signal based on LMD, and to obtain the instantaneous amplitude of the signal from the PF components of the amplitude modulation function. Then, to apply the Hilbert transform to obtain the instantaneous frequency of PF. The improved LMD method could effectively locate the beginning and ending time of the disturbances occurred and overcome the deficiencies of the LMD positioning capability. By using the method, the curves of the instantaneous amplitude had less distortion in wave head and that of the instantaneous frequency had shorter swings, and detection results for magnitude and frequency of disturbance signal had higher accuracy, compared with the HHT method. The simulation and experimental results of the switch voltage analysis of capacitor group from 500 kV transformer substation prove the feasibility and effectiveness of the proposed method.

【基金】 国家自然科学基金项目(51307152,60974005);郑州市科技攻关项目(121PPTGG364-3)~~
  • 【文献出处】 中国电机工程学报 ,Proceedings of the CSEE , 编辑部邮箱 ,2014年10期
  • 【分类号】TM711
  • 【被引频次】96
  • 【下载频次】1112
节点文献中: 

本文链接的文献网络图示:

本文的引文网络