首钢京唐1号高炉配加湿熄焦冶炼实践
Practice of No.1 BF Smelting with Wet Quenched Coke in Jingtang Steel
【摘要】 首钢京唐焦化厂年修期间,1号高炉配加湿熄焦比例最高70%,通过采取适当提高焦比、调整装料制度、合理提高铁水中[Si]等措施,高炉顺行状态良好,平均日产12793t/d,焦比328.4kg/t,燃料比516.5kg/t。
【Abstract】 During overhaul period of Jingtang Steel’s Coking Plant,the wet quenched coke charged into No.1 BF accounts for 70%max.However the blast furnace still operates smoothly thanks to the measures of increasing the coke ratio,regulating the charging system and rationally heightening[Si]content in hot metal.The ave.daily output reaches 12793t/d under coke ratio of 328.4kg/t and fuel ratio of 516.5 kg/t.
【关键词】 特大型高炉;
配加;
湿熄焦;
冶炼;
【Key words】 super large sized blast furnace; charge; wet quenched coke; smelting;