节点文献

分期施工深基坑支护换撑结构的优化及施工

Optimization and Construction of Bracing Substitution of Deep Foundation Excavation Support by Stage Construction

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 沈兴东张具林徐旭汪仲琦

【Author】 Shen Xingdong;Zhang Julin;Xu Xu;Wang Zhongqi;The Third Construction Co. ,Ltd. of China Construction Eighth Engineering Division;

【机构】 中建八局第三建设有限公司

【摘要】 介绍了南京金陵饭店扩建工程3层地下室结构分期施工所采用的大截面换撑梁施工技术,具体阐述了换撑梁的设计优化、施工及拆除技术,详细描述了实际施工中所采取的技术措施。既解决了大截面换撑梁的施工安全问题,又确保一、二期地下室结构施工时水平支撑有效对接,实现了分期施工地下室混凝土结构的有效连接。

【Abstract】 Based on Nanjing Jinling Hotel expansion project,this paper introduced the construction technology of large cross-section support replacement beam adopted in three layer basement structure during construction in phases, specifically expounded the design optimization, construction and demolition technology of support replacement beam, described a series of technical measures in detail. Furthermore,the technology not only solved the safety problems of large cross-section support replacement beam,but also ensured the effective docking of horizontal support when the first and second phase basement structure is under construction. The effective docking of basement structure during construction in phases is finally completed.

【基金】 中国建筑第八工程局有限公司科技开发立项项目(2011-03)
  • 【文献出处】 施工技术 ,Construction Technology , 编辑部邮箱 ,2014年01期
  • 【分类号】TU753
  • 【被引频次】5
  • 【下载频次】209
节点文献中: 

本文链接的文献网络图示:

本文的引文网络