ZRF25型放射性可燃固体废物焚烧装置“冷态试车”工程验证
Non-radioactive Verification Test of ZRF25 Radioactive Combustible Solid Waste Incinerator
【摘要】 介绍了我国某厂"ZRF25型放射性可燃固体废物焚烧装置"的冷态试车工程验证情况,通过24 h、72 h及168 h的模拟物料连续运行试验,得出结论:该装置工艺可行、整体运行平稳、安全可靠;焚烧装置处理能力、减容比、焚烧灰热灼减率等各项技术指标均满足合同书及国家有关标准要求。
【Abstract】 This paper mainly introduces the construction and test run of ZRF25 radioactive combustible solid waste incinerator,by a series of simulating waste tests,such as 24 h test,72 h test,168 h test,making a conclusion that the incinerator runs reliably. In addition,all of the indexes( such as treatment capacity,volume reduction coefficient,clinker ignition loss of incineration ash) meet the requirements of contract and pollution discharging standards.
【关键词】 放射性废物;
焚烧;
冷态试车;
工程验证;
【Key words】 radio-active waste; incineration; test-run; engineering-scale verification;