龙华口碾压混凝土大坝施工布置
On Construction Layout of Longhuakou Roller Compacted Concrete Dam
【摘要】 龙华口水电站工程由于前期征地困难的原因,未能按照投标时的规划方案进行临建设施布置,后将大坝主要生产设施布置在坝前范围内,其关键在于要做好各项防护设施,以确保施工期安全。文中详细描述了原招标阶段的施工布置方案和现在的方案。
【Abstract】 Because of encountering difficulty to requisition farmland for construction,the Longhuakou Hydroelectric Project’s layout of temporary installations for construction was not adopted according to the preliminary plan which was presented during the bidding period.At present,the main temporary structures are located on the upstream of dam site.The key points of layout are to make a good job on assorted protect measures,to ensure construction period’s safety.The paper introduces the construction layouts during the bidding period and at present in detail.
- 【文献出处】 山西水利科技 ,Shanxi Hydrotechnics , 编辑部邮箱 ,2011年01期
- 【分类号】TV511
- 【下载频次】26