节点文献

京沪高速铁路桩端注浆群桩基础数值模拟研究

Study on Numerical Simulation of Pile Group Foundation by Pile Tip Grouting in Beijing-Shanghai High-speed Railway

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 邹力吴兴序马建林

【Author】 ZOU Li,WU Xing-xu,MA Jian-lin(School of Civil Engineering,Southwest Jiaotong University,Chengdu 610031,China)

【机构】 西南交通大学土木工程学院

【摘要】 以往对于桩基后注浆技术的研究大多局限于单桩,而目前各类工程中桩基础的结构形式是群桩所占比重大,在设计上都以变形控制为主。使用FLAC3D有限差分软件,针对京沪高速铁路桩基后注浆试验段中群桩基础在正常使用状态下的计算机模拟静载试验,研究其荷载-沉降规律,验证在设计荷载作用范围内,群桩桩端注浆减小群桩基础沉降量的效果。

【Abstract】 The previous studies on pile foundation post-grouting technology are mainly limited to single pile.However,group pile is the major structure of pile foundation in engineering at present,which is designed based on deformation control.According to computer simulation static test of group pile foundation in Beijing-Shanghai high-speed railway post-grouting test section under normal state,the load-settlement law is studied using FLAC3D finite difference software.It is verified the effect of pile tip grouting on reduction of group pile foundation settlement within design load.

【基金】 铁道部科技研究开发计划重大课题:京沪高速铁路桥梁桩基后注浆技术试验研究(2008G032-3)
  • 【文献出处】 路基工程 ,Subgrade Engineering , 编辑部邮箱 ,2011年02期
  • 【分类号】U238;U213.1
  • 【被引频次】7
  • 【下载频次】146
节点文献中: 

本文链接的文献网络图示:

本文的引文网络