节点文献
关于特长公路的隧道施工分析
The Analysis of Tunnel Construction of Special Long Roads
【摘要】 介绍了石牙山隧道的工程概况、工程特点、施工方法以及具体施工过程中通风、用电、防排水和该隧道的施工方案。隧道施工密切结合新奥法—复合衬砌施工精髓进行。
【Abstract】 The article intruduces the engineering profile and characteristics of Shiya Mountain Tunnel,its construction methods and its ventilation,electricity consumption,waterproof and drainage system as it was constructed and the construction plan of the tunnel.The construction closely combines new methods that compound lining construction.
【关键词】 核心土;
正台阶开挖法;
全断面开挖法;
初期支护和长管棚;
【Key words】 core soil; heading-and-bench excavation method; over-sectional excavation; preliminary timbering and long-pipe shed;
【Key words】 core soil; heading-and-bench excavation method; over-sectional excavation; preliminary timbering and long-pipe shed;
- 【文献出处】 企业科技与发展 ,Enterprise Science and Technology & Development , 编辑部邮箱 ,2010年02期
- 【分类号】U455.4
- 【下载频次】55