7.63m焦炉投产后存在的问题及解决办法
Problem existed after 7.63m coke oven commissioning and solution
【摘要】 介绍了太钢7.63m焦炉投产后单炉装煤量不足、炉顶空间温度高、炼焦耗热量高、炭化室压力波动大、焦炭水分不稳定等问题。通过2年多的实践与探索,解决了生产中的这些难题,现在每天出炉134炉,日产焦炭6000t,达到了设计能力。
【Abstract】 The problems such as single oven insufficient coal charge, high temperature on oven free space, high heat consumption for coke-making, big fluctuation of oven chamber pressure, un-stable coke moisture after the commissioning of 7.63m coke oven at TISCO were described.Through practice and study for 2 years or more, these problems occurred in production have been solved.Now 7.63m coke oven can push 134 ovens per day, the daily coke production is 6 000t, which has reached to the design parameters.