上海地区③土层上无桩基础水闸实测沉降资料分析

Analysis on In-situ Settlement Measurement of Sluice without Piles Located on ③ Soil Stratum in Shanghai

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 付新永杜占鹏姚顺雨徐兵

【Author】 FU Xing-yong1,DU Zhan-peng2,YAO Shun-yu1,XU Bing3(1.Shanghai Qingcaosha Investment Construction & Development Co.,ltd.,Shanghai 201206,China;2.Zhejiang Provincial No.1 Water Conservancy & Electric Power Construction Group CO.,Lcd.,Hangzhou 310051,China;3.Science & Research Department of Shanghai Investigation,Design & Research Institute Shanghai,Shanghai 200434,China)

【机构】 上海青草沙投资建设发展有限公司浙江省第一水电建设集团有限公司上海勘测设计研究院科研所

【摘要】 基于上海地区③土层上的一座无桩基础水闸——祝家港节制闸闸室的沉降资料,分别对沉降曲线本身、用双曲线配合法对地基土的最终沉降量进行预测及地基土沉降与地基反力的关系这3个方面进行了分析。分析结果表明:上海地区③土层上无桩基水闸施工期的沉降量一般在-40 mm左右,沉降曲线在水闸通水后一般都经历一个月的"假收敛期";从用双曲线配合法推求的地基最终沉降量预测值来看,施工期③土层的瞬时沉降(弹/弹塑性变形)sd占最终沉降量的比例为25%~50%,S∞后续的大部分沉降都要在竣工后的长期使用期间内再发生;结合地基反力的测试结果来看,③土层地基反力与变形相互协调变化。

【Abstract】 On the basis of the measured displacements from the chamber of a check sluice in Zhujia Harbor,the total settlements obtained from the time-settlement curve and hyperbolic matching method were compared.The relationship between displacement and foundation resistance was analyzed.The check sluice was built directly on the 3rd stratum of Shanghai clay with no piles underneath.The results showed that:(1) the sluice settlement during construction period was about-40 mm;(2) a typical pseudo-convergence would occur on the time-settlement curve during the first month after the sluice running;(3) the settlement data predicted by the hyperbolic matching method indicated the transient(elastic/elastoplastic) settlement was about 25%-50% of the total settlement,of which the rest will appear again in a long time after construction;(4) the measured resistance in the 3rd stratum of Shanghai clay was concordant with the measured displacement.

  • 【文献出处】 长江科学院院报 ,Journal of Yangtze River Scientific Research Institute , 编辑部邮箱 ,2009年08期
  • 【分类号】TV698.1