节点文献
山东高压试验大厅接入系统若干问题及解决措施探讨
Discussion and Solutions to Shandong High-voltage Test Hall Connected to the Grid
【摘要】 应用中国电科院的PSASP程序,对山东电力研究院高压试验大厅接入电网所产生的若干问题进行了计算分析,并针对性地提出了解决措施。
【Abstract】 PSASP applied in the paper, the problems raised by the Shandong high-voltage test hall connected to the grid are discussed, and then the solutions are put forward.
【关键词】 变压器;
高压试验;
负序电流;
三相电压不平衡;
零序电压;
【Key words】 transformer; high-voltage test; negative-sequence current; three-phase voltage unbalance; zero-sequence voltage;
【Key words】 transformer; high-voltage test; negative-sequence current; three-phase voltage unbalance; zero-sequence voltage;
- 【文献出处】 山东电力技术 ,Shandong Electric Power , 编辑部邮箱 ,2008年05期
- 【分类号】TM733