万家寨引黄工程北干煤矿采空区垂直变形监测网的实施
The Implementation of Vertical Deformation Monitoring Network of Coal Gob Area in North Trunk of Wanjiazhai YRDP(Yellow River Diversion Project)
【摘要】 介绍了万家寨引黄工程北干线煤矿采空区变形监测的目的,阐述了垂直变形监测网的建立及监测结果。
【Abstract】 This paper introduces the aims of vertical deformation monitoring of coal gob area in north trunk of Wanjiazhai YRDP,expounds the establishment of vertical deformation monitoring network and monitoring results.
【关键词】 垂直变形监测;
工作基点;
监测点;
测量精度;
【Key words】 vertical deformation monitoring; working reference point; monitoring point; measurement accuracy;
【Key words】 vertical deformation monitoring; working reference point; monitoring point; measurement accuracy;