【摘要】 介绍了锦屏一级水电站化学灌浆试验研究及施工情况,明确在此类地质条件下采用化学灌浆是完全必要且可行的,整个试验取得了成功,对今后工程的实施及类似工程项目的试验研究具有借鉴意义。
【Abstract】 Based on an introduction of the testing and construction of chemical grouting at Jingpin I Hydropower Plant,it is concluded that chemical grouting is necessary and feasible under such geological conditions.The success of testing provides reference for construction and testing of similar projects in the future.
- 【文献出处】 广西水利水电 ,Guangxi Water Resources & Hydropower Engineering , 编辑部邮箱 ,2008年03期
- 【分类号】TV543.2
- 【被引频次】8
- 【下载频次】49