节点文献
梯级水库下游工程施工导流流量优化设计研究
Study on the Optimal Design of Flood Diversion for the Construction Period of Downstream Cascade Reservoir
【摘要】 通过汛期临时改变梯级水库上游可调节水库运行方式,提出减小梯级水库下游工程施工导流流量的优化设计方法,并以黄河上游积石峡水电站施工导流流量的优化设计为例进行分析计算。
【Abstract】 The optimal design method which the flood diversion for the construction period can be reduced for construction of the downstream cascade reservoirs by changing reservoir operation for regulation reservoir on the upper reaches of cascade reservoir was presented in the paper.The example of flood diversion for the construction period of Jishixia project on upper reaches of the Yellow River was included.
【关键词】 施工导流流量;
防洪标准;
汛限水位;
下泄流量;
【Key words】 flood diversion for the construction period; flood control standard; flood control level; discharge flow;
【Key words】 flood diversion for the construction period; flood control standard; flood control level; discharge flow;
- 【文献出处】 西北水力发电 ,Journal of NOTHUCEST rYDOOELECTNICPOWER , 编辑部邮箱 ,2005年03期
- 【分类号】TV551.1
- 【被引频次】5
- 【下载频次】122