局部桩基础和复合地基上的土石坝三维分析
Three-dimensional Analysis of Earth-Rock Dams on Local Pile Foundation and Composite Foundation
【摘要】 结合太仓市第二水厂蓄淡避咸水库大坝的地基加固处理工程,针对桩基础和桩长纵向渐变复合地基,应用三维快速拉格朗日法对较大规模群桩进行计算,分析了不同桩径、桩距和桩长复合地基对坝体和坝基的应力、位移的影响。
【Abstract】 Combining the engineering of ground consolidation treatments of the2nd Water Treatment Plant Dam in Taicang City ,in view of the pile foundation and composite foundation of laterally gradual change in length of pile ,with three-dimensional fast Lagrangian analysis program,following items are analyzedi Influence of different pile spacing,different pile diameter and different pile length of composite foundation on stress and displacement of dam and foundation.