境界顶柱稳定性的数值模拟研究
Numerical Simulation of the Stability of Boundary Pillar
【摘要】 露天转地下开采的矿山 ,其境界顶柱稳定性将直接影响到矿山的安全生产。本文以石人沟铁矿为例 ,运用ANSYS有限元分析软件 ,建立三维数值模型 ,模拟了动载荷作用下分步回采引起顶柱及采场的应力、变形情况 ,并对结果进行了详细的分析 ,得出了有价值的结论 ,有利于指导矿山的安全生产
【Abstract】 For a mine to be changed from an open pit to underground stope, the stability of the boundary pillar has direct influences on the safety production of the mine. Taking Shirengou Iron Mine as an example, a three-dimensional numerical model is built with a finite element analytical software to simulate the stress and distortion of the pillar and stope caused by fractional stoping under dynamic load. The results were analyzed in detail, which reaches a conclusion useful for guiding safety production of the mine.
【关键词】 露天转地下;
有限元;
数值模拟;
境界顶柱;
【Key words】 change from an open pit to underground stope; finite element; numerical simulation; boundary pillar;
【Key words】 change from an open pit to underground stope; finite element; numerical simulation; boundary pillar;
- 【文献出处】 矿冶工程 ,Mining and Metallurgical Engineering , 编辑部邮箱 ,2004年06期