瀑布沟水电站泄洪洞开挖变形和稳定性分析
Excavation Deformation and Stability Ana lysis of Spillway Tunnel of Pubuguo Hydr opower Station
【摘要】 瀑布沟水电站泄洪洞右侧壁最小厚度仅约10 0m,左侧山体高达100 0m,隧洞偏压问题突出。本文采用非线性有限元法,研究隧洞在开挖过程中,边坡的稳定性和隧洞的偏压应力。
【Abstract】 The minimum depth of the spillway tunnel from the slope s urface on the right side is only 10m whi le on the spillway left side the mountia n has a height of 100m.Therefore,the in situ stress on the right side of the spi llway tunnel is much higher than that on the left side.In this paper stability o f the slope and unbalanced side pressure of the spillway tunnel during its excav ation are studied by using nonlinear fin ite element method.
【关键词】 泄洪隧洞;
隧洞开挖;
岩体变形;
稳定分析;
有限元法;
瀑布沟水电站;
【Key words】 spillway tunn el; tu nnel excavation; deformation of rock mass; stability analysis; finite element metho d; Pubuguo Hydropower Station;
【Key words】 spillway tunn el; tu nnel excavation; deformation of rock mass; stability analysis; finite element metho d; Pubuguo Hydropower Station;
- 【文献出处】 水电站设计 ,Design of Hydroelectric Power Station , 编辑部邮箱 ,2003年02期
- 【分类号】TV223
- 【被引频次】7