新奥法在天堂山拱坝左坝肩断层处理工程中的应用
Application of Xinao Method to Handle Fault of the Left Shoulder of Tiantangshan Arch Dam
【摘要】 天堂山拱坝左坝肩断层处理工程的施工开挖过程中 ,在地质、施工条件极为不利的情况下 ,运用新奥法 ,控制开挖质量 ,采用锚杆与木结构相结合的支护方法 ,大大加快了施工进度 ,节约工期 ,保证了施工质量与安全 ,取得了明显的经济效益
【Abstract】 This paper introduces the new underground building construction method to control excavating quality and use support method of anchor poles combined with timber structure under excavating construction to handle the fault in the left shoulder of Tiantangshan arch dam because the condition of geology is not good,therefore that speeded construction rate,shortened construction period,ensured the construction quality and safety,and the same time obvious economic benefit had been gained.
【关键词】 天堂山拱坝;
左坝肩;
断层处理;
新奥法;
安全支护;
【Key words】 Tiantangshan arch dam; the left shoulder of dam; fault handled; excavating; the new underground building construction method; support for safety;
【Key words】 Tiantangshan arch dam; the left shoulder of dam; fault handled; excavating; the new underground building construction method; support for safety;
- 【文献出处】 吉林水利 ,Jilin Water Resources , 编辑部邮箱 ,2003年01期