宝钢1号高炉开炉实践
Practice of Baosteel No.1 BF blow-in
【摘要】 经过烘炉、装料和料面测量等准备工作后,宝钢1号高炉第二代炉役于1997年5月25日顺利开炉。开炉后,高炉炉况顺行稳定,第15天(6月9日)日产量即达8116t,高炉利用系数达2.01。开炉后第一个月高炉主要技术经济指标创宝钢高炉历次开炉先进水平。
【Abstract】 The No.1 BF of Baosteel was put into operation on May 25 of 1997 after baking furnace, filling and charge level measure. The BF was operated smoothly, and on the fifteenth day the daily-output reached 8116 tons and the productivity hit 2.01 t/(m3·d).As a result, good product indexes were obtained in the first month.
- 【文献出处】 炼铁 ,Iron Making , 编辑部邮箱 ,1997年06期