秦山核电厂反应堆压力容器水压试验应变测量与分析

STRAIN MEASUREMENT AND ANALYSIS FOR THE RPV OF QINSHAN NPP(UNIT I ) AT PRIMARY SYSTEM HYDROSTATIC TEST

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 曲家棣; 王佩珠; 谢世球; 陈仁锠; 盛贤科; 窦一康; 赵卫良;

【Author】 QU JIADI WANG PEIZHU XIE SHIQIU CHEN RENCHANG SHENG XIANKE DOU YIKANG ZHAO WEILIANG(Shanghai Nuclear Engineering Research and Design Institute)

【机构】 上海核工程研究设计院; 上海核工程研究设计院;

【摘要】 对秦山核电厂反应堆压力容器出厂水压试验测点布置作了说明,与一回路系统水压试验位移测量的主要结果作了分析对比,给出了实测载荷与主螺栓测试数据,讨论了表征密封性能的法兰转动,认为出厂水压试验此项结果有错.

【Abstract】 Hydrostatic test for RPV is not only a means to inspect the vessels and the associated systems but also an important way to verify the results of mechanical analysis. The loading obtained by measurement is useful for the establishment of loading spectrum. In this paper, some discussions on the shop hydrostatic test planning for the RPV of Qinshan NPP performed in Japan are presented. Comparisons between the results of hydrostatic test provided by vendor and those of primary system hydrostatic test conducted at Qinshan Site are also given. Some data obtained at Qinshan Site such as actual loading and technical data of the stud - bolt, are listed. The results of measurement for the flange rotation, important for the sealing characteristics of RPV, are specifically discussed. This paper points out some of the mistakes in the results of the shop hydrostatic test.

  • 【文献出处】 核科学与工程 ,Chinese Journal of Nuclear Science and Engineering , 编辑部邮箱 ,1994年01期
  • 【分类号】TL375
  • 【被引频次】1
  • 【下载频次】147