节点文献
350MW机组锅炉给水控制系统中的新策略
New Strategies of Boiler Feedwater Control System in 350MW unit
【摘要】 上安电厂一期工程锅炉给水控制系统采用了许多新的控制方法和策略,本文仅对其中的平衡电路,单冲量切换三冲量控制,甩负荷时给水主副调节器“闭锁”问题进行分析,并介绍了调试中的改进和尚待解决的问题.
【Abstract】 Shang An power plant is a sub-contrd loop of Network-90 system. May new control methods and strategies are used to control the whole load range of drumlevel. The circuit balancing.the control transferring from single -impulse to three-impulse and the controller "Look up" proble in case of load rejection are discussed in this paper. The paper also introduces some improvements and problems not solved during commissioning.
- 【文献出处】 河北电力技术 ,Hebei Electric Power , 编辑部邮箱 ,1991年S1期
- 【下载频次】42