资源强制限定时工期最短方案的确定方法
A NEW METHOD DETERMINING SHORTEST DURATION PLAN IN THE CONDITIONS OF RESTRICT SOURCES
【摘要】 本文提出了在资源严格限定条件下,工期最短方案的一种新的确定方法。利用优先系数进行工程的安排,不仅使工期最短、资源利用率最高,而且还采用试探调整法使工程尽可能地连续施工。
【Abstract】 In this paper, a new method determining shortest duration plan in the conditons of restrict sources is proposed. The construct priority coefficient is used to arrange the engineering, the arranged duration is shortest, the sources utilization ratio is highest, and the trial adjustment method is used to construct the engineering as continuous as posible.
【关键词】 资源限定;
工期最短;
施工优先系数;
制约时差;
试探调整法;
连锁工程横道图;
【Key words】 sources restricted; shortest construction duration; construct priority coefficient; restrict float; trial adjustment method;
【Key words】 sources restricted; shortest construction duration; construct priority coefficient; restrict float; trial adjustment method;
- 【文献出处】 阜新矿业学院学报 , 编辑部邮箱 ,1988年04期